Delayed Tasks Summary

The Delayed Tasks Summary report helps identify the tasks which have exceeded their Expected End Dates.

To view this report, you can go to:

Home > Projects > Reports > Delayed Tasks Summary

The report is generated based on the Task Doctype.

Delayed Tasks Summary

Calculation of Delay

Tasks have a date field called Completed On, which becomes visible when a Tasks status is changed to Completed.

Scenario 1

If a task is marked as Completed and the Completed On field is set, then the delay is calculated as the difference between the Completed On and the Expected End Date.

Delay = Completed On - Expected End Date
Scenario 2

If the Completed On field is not set, then the delay is calculated as the difference between the current date and the Expected End Date.

Delay = Current Date - Expected End Date

Chart

The chart shows the number of tasks that are On Track or Delayed based on the report generated after applying the filters.

Discard
Save
Was this article helpful?

On this page